Grids & Industry · France
Saint-Pierre-des-Corps industrial depot
New MV loop and redesign of the power architecture of a heavy maintenance depot.
4architectures studied
6HV substations fed
12 MVAinstalled
2023–2026Period
The assignment
New MV loop and redesign of the power architecture of a heavy maintenance depot.
The challenge
Until now fed from an SNCF Réseau substation, the depot must become independent: new MV loop, renewal of obsolete installations and room for future needs.
Our approach
Options study with several supply architectures, preliminary design of the selected one and follow-up of the Enedis connection request.