Marseille Blancarde depot
Return to service and upgrade of the depot's 25 kV substation, out of service since 2016, to supply two workshops again.
The assignment
Return to service and upgrade of the depot's 25 kV substation, out of service since 2016, to supply two workshops again.
The challenge
After a fault on the site's 25 kV coaxial supply cable, SNCF Voyageurs needs to test its trains at 25 kV. The existing 25 kV substation has been out of service since 2016: it must be brought back into service and up to standard to supply two workshops at 25 kV from the site's internal 20 kV loop.
Our approach
TRACTEDIS carries out the preliminary design and drafts the EALE tender documents: specification, cable routing plan, layout plan, technical specification list, substation single-line diagrams, power balance, HV and LV calculations.
Similar projects
A similar project? Let’s talk
A fast answer from the office closest to your project.