Grand Paris Express: traction substation testing, lines 16 and 17

Testing of the rectifier and sub-sectioning substations powering the two automated metro lines.

10rectifier substations
18sub-sectioning posts
55.5 kmof track
68.2 MVAinstalled
2023–2026Period

The assignment

Testing of the rectifier and sub-sectioning substations powering the two automated metro lines.

The challenge

Rectifier substations feed the overhead line and sub-sectioning posts split the lines into sections: each must be verified before service.

Our approach

Phase 2.1: visual checks, continuity and insulation of cables, HV switchgear and panels, earthing, interlocking. Phase 2.2: LV commissioning, MV protection tests, opening and closing times. Then HV commissioning tests.

Project owner
Société des grands projets
Engineer
Egis / Setec
Contractor
Equans
Chargé d'essais
TRACTEDIS
TRACTEDIS role
Procedures, test books and on-site testing (phases 2.1, 2.2 and HV commissioning)
Assignment
Testing & commissioning
System and voltage
1,500 V DC / MV
Country
France
Period
2023–2026
Certificate
On request