EOLE: tunnel ventilation and smoke extraction

Supervision of ventilation works and their power supply in 9 shafts and Porte Maillot station.

9shafts
3stations
8 kmof tunnel
2016–2024Period

The assignment

Supervision of ventilation works and their power supply in 9 shafts and Porte Maillot station.

The challenge

Between La Défense and Haussmann–Saint-Lazare, 9 shafts and Porte Maillot station receive the tunnel ventilation and smoke extraction systems.

Our approach

Supervision of fan and equipment installation, LV distribution (drives, PLCs, cable trays) and power and fibre connections to the supervision system; civil works interfaces, reporting and air-flow and electrical test follow-up.

Project owner
SNCF
Engineer
SED (Setec, Egis, Duthilleul)
Contractor
Ineo, Yvroud, Axima
TRACTEDIS role
Works supervision
Assignment
Engineering & supervision
System and voltage
LV
Country
France
Period
2016–2024
Certificate
On request