Grids & Industry · France

Bois-Bernard 225 kV source substation

New 225 kV source substation shared with Enedis, cut into the Gavrelle–Vendin no. 2 line.

225 kVsource substation
34 monthsassignment
15FTE on average
€3.1mproject cost
2023–2026Period

The assignment

New 225 kV source substation shared with Enedis, cut into the Gavrelle–Vendin no. 2 line.

The challenge

RTE's scope covers the busbar, two line bays and gantries, a shared RTE/Enedis building, two relay buildings, control, telecontrol, metering and the update of protection and teleprotection at neighbouring substations.

Our approach

Building permit, preliminary and detailed design, contract award assistance, approval of construction studies, works management and coordination, acceptance support.

Project owner
RTE
Engineer
TRACTEDIS / Setec / SCE
Client
Enedis (poste coexploité)
TRACTEDIS role
Lead engineering, from building permit to acceptance
Assignment
Design, Engineering & supervision
System and voltage
225 kV
Country
France
Period
2023–2026
Certificate
On request