Grids & Industry · France
Bois-Bernard 225 kV source substation
New 225 kV source substation shared with Enedis, cut into the Gavrelle–Vendin no. 2 line.
225 kVsource substation
34 monthsassignment
15FTE on average
€3.1mproject cost
2023–2026Period
The assignment
New 225 kV source substation shared with Enedis, cut into the Gavrelle–Vendin no. 2 line.
The challenge
RTE's scope covers the busbar, two line bays and gantries, a shared RTE/Enedis building, two relay buildings, control, telecontrol, metering and the update of protection and teleprotection at neighbouring substations.
Our approach
Building permit, preliminary and detailed design, contract award assistance, approval of construction studies, works management and coordination, acceptance support.