Transport · France
1,500 V preconditioning sockets, Avignon depot
New MV substation and three 1,500 V preconditioning sockets for the Marseille–Nice TER Corail coaches.
1new MV substation
3preconditioning reels
160 kVApreconditioning
2023–2025Period
The assignment
New MV substation and three 1,500 V preconditioning sockets for the Marseille–Nice TER Corail coaches.
The challenge
After the Marseille–Nice line changed operator in 2025, part of the Corail coach maintenance moves to the Avignon depot, which needs a 1,500 V preconditioning network.
Our approach
Detailed design and tender for the MV substation and 3 preconditioning points, then test documents (procedures, test books, reports, snag lists) and phase 2.1 (technical checks, earth measurements), 2.2 (LV energisation, opening times, contact resistance, protection) and 2.3 (functional tests, interlocking) testing.